The underpass for the Skyline Trail, one of several improvements that were part of the Sterling Highway Mile 58 to 79 Improvements Project, provides a safe crossing for hikers. (Photo provided by Kenai National Wildlife Refuge)

The underpass for the Skyline Trail, one of several improvements that were part of the Sterling Highway Mile 58 to 79 Improvements Project, provides a safe crossing for hikers. (Photo provided by Kenai National Wildlife Refuge)

Refuge Notebook: Completion of the Sterling Highway Improvements Project

As anyone visiting the Skilak Lake Wildlife Recreation Area or traveling between the Kenai Peninsula and Anchorage knows, construction has been underway on the Sterling Highway Mile 58 to 79 Improvements Project since June 2017. There is an end in sight though, as the remaining roadwork is scheduled for completion by the end of June this year.

What is left to do within the Sterling Highway right of way? Adding topsoil and seeding, finishing slope stabilization and ditches, final striping, and installing permanent regulatory and information signs remain.

While most of this work should not result in traffic delays on the highway, Granite Construction, contractor for the Alaska Department of Transportation and Public Facilities, does anticipate delays during the final striping efforts, which will occur over a two-week period.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Weather permitting, Granite Construction plans to begin the remaining work in May 2020 and be finished with Sterling Highway work no later than the end of June.

The project, 18 miles of which cross the Kenai National Wildlife Refuge, involved the installation of three sets of passing lanes; widening the shoulders to 8 feet; repair, replacement and improvement of storm-water drainage facilities under the highway; erosion protection; upgrading vertical and horizontal curves as needed; utilities relocation; guardrails and signage.

In addition, much-needed wildlife crossing structures have been installed, consisting of a 140-foot long by 43-foot wide by 18-foot high bridge, plus five additional wildlife under-crossings at strategic locations throughout the corridor.

The new bridge not only provides a safe passage for wildlife to move under the highway, but it also improves fish passage up and down the East Fork Moose River, which is an anadromous stream. For further details on these wildlife crossing structures see Dr. John Morton’s Refuge Notebook article from January 2019.

Public access from Skyline Trail parking on the south side of the Sterling Highway to the trail on the north side has also been greatly improved and made much safer with the installation of a pedestrian tunnel under the highway. We hope that visitors will be able to enjoy this new pedestrian tunnel once we are able to reopen the Skyline Trail.

Impacts to the Skyline Trail from the 2019 Swan Lake Fire were substantial, yet while the trail is currently closed, repairs should be completed this summer. The refuge will be adding a second trail crew this summer to focus on opening and restoring the five trails damaged by the Swan Lake Fire that remain closed (Skyline Trail, Kenai River Trail, Seven Lakes Trail, Hideout Trail and Surprise Creek Trail).

Other work that Granite Construction will be completing this summer will not affect Sterling Highway drivers but will be noticeable to refuge visitors this fall. For many years, access off the Sterling Highway to Mystery Creek Road has been a safety concern as it was located on a curve and the access road was steep.

During winter, snowmachiners and mushers had to park a half mile away and then go cross-country to reach Mystery Creek Road in order to then travel on the road to access various places in the Mystery Creek watershed.

The Mile 58 to 79 project provided an opportunity to obtain a safer intersection and enhanced visitor parking. Mystery Creek Road is now being realigned, in conjunction with relocating its intersection with the Sterling Highway, and a parking area near this new intersection is being constructed.

These enhancements will provide additional public access to the Mystery Creek and Mystery Hills area. This road realignment and enhancement work should be completed later this summer, just in time for the Mystery Creek Road opening this fall. That opening usually occurs the second week in August.

Associated with the Mystery Creek Road realignment will be the restoration of one of the material sites utilized for the Mile 58 to 79 project. This material site is located where the new alignment of Mystery Creek Road will terminate, near Mile 63.

Once the remaining work along the highway corridor is complete, the contractor will begin a major reclamation effort at this site.

The restoration work will enhance the existing disturbed area by softening slopes and reshaping the bottom of the pit, which includes placing overburden and organics removed during grubbing work along the highway to provide a more natural rolling and diverse topography.

The entire material site will be revegetated using native plants and seeds, which will help facilitate return to a more natural vegetated state over time.

We envisioned this effort would, over the course of the coming decades, eventually result in the restoration of the site to mimic the adjacent, natural forested area. However, with the surrounding intact forest being significantly changed by the Swan Lake Fire, natural recolonization of the fire-impacted landscape and the planned reclamation effort at the extraction site will be occurring simultaneously.

All of this work is being completed just in time for the start of the Sterling Highway Mile 45 to 60 project, or the Cooper Landing bypass, coming soon. …

Lynnda Kahn serves as Fish and Wildlife Biologist at the Refuge. She represents the Kenai NWR as oil/gas liaison, ensuring compliance with habitat conservation and management policies; and as Permits Coordinator for utility and transmission lines, pipelines and highway improvements that occur within the various right of ways on refuge land. Find more Refuge Notebook articles (1999–present) at https://www.fws.gov/Refuge/ Kenai/community/Refuge_notebook.html


By LYNNDA KAHN

Kenai National Wildlife Refuge


More in Sports

tease
Thursday: Twins finish strong road trip by sweeping South

The visiting American Legion Post 20 Twins picked up 10-0 and 18-5… Continue reading

Nick Varney
Reeling ‘Em In: Fair weather expected for 4th of July weekend

Keep a heads-up approach when in traffic during the holiday — you don’t know who you’ll run into.

tease
Post 20 Twins enact mercy rule on Eagle River

The visiting American Legion Post 20 Twins defeated Eagle River 11-0 in… Continue reading

tease
Tri Nikiski draws 79 participants

The ninth annual Tri Nikiski was held Saturday starting from the Nikiski… Continue reading

Runners start from Homer High School during the Homer Spit Run 10K to the Bay on Saturday, June 28, 2025, in Homer, Alaska. (Delcenia Cosman/Homer News)
Running to the finish

The Homer Spit Run on Saturday drew nearly 250 participants.

The Peninsula Oilers have announced the sale of their building at 601 
S. Main Street in Kenai, Alaska. (Photo by Jeff Helminiak/Peninsula Clarion)
Oilers look to sale of building to return to field in 2026

This is just the second summer since 1974 that the Peninsula Oilers… Continue reading

tease
Sunday: Twins lose in semis of Midseason Classic

The American Legion Post 20 Twins lost 14-1 in five innings to… Continue reading

Soldotna's Beau Johnson competes in Chute Dogging on Saturday, June 28, 2025, in the second Soldotna Equestrian Association rodeo of the year at the Soldotna Rodeo Grounds in Soldotna, Alaska. (Photo by Jeff Helminiak/Peninsula Clarion)
Soldotna Equestrian Association holds 2nd rodeo of season

The Soldotna Equestrian Association is holding its second rodeo of the season… Continue reading

Most Read