Work allowed to progress on 3 large-scale projects

  • By Becky Bohrer
  • Tuesday, July 14, 2015 11:15pm
  • News

JUNEAU — Gov. Bill Walker’s administration is allowing work to progress on three large-scale infrastructure projects, but he has not yet given a final blessing.

Recent memos from Walker’s budget director, Pat Pitney, outlined allowable work on the Knik Arm Bridge, a road from Juneau and the Susitna-Watana dam. The work is to be completed with existing funding for the projects.

In December, Walker halted new, unobligated spending on those and several other major projects pending further review, citing a fall in oil prices that contributed to large state budget deficits.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The state transportation department had raised concerns that Alaska could face penalties, including potentially having to repay federal money, if the Knik Arm and Juneau projects were stopped or suspended.

For the Knik Arm project, which would connect Anchorage to land near Point MacKenzie in the Matanuska-Susitna Borough, the allowable work includes submitting a letter of interest for a federal loan. Under a bill passed last year by state lawmakers, such a loan would represent a critical piece of funding for the project.

Bob French, a critic of the project, said Tuesday that if the project gets turned down for a loan, he hopes Walker would see that as the federal government saying the project doesn’t make financial sense and therefore should be dropped.

For the Juneau project, the allowable work includes completing an environmental impact report and reaching a so-called record of decision in which a preferred alternative would be identified.

Pitney, in a memo to transportation commissioner Marc Luiken dated July 6, said reaching a record of decision would ensure the state does not have to repay nearly $27 million in federal funds. The project will be evaluated once that milestone is reached. Based on the findings and state revenues, a decision will be made on how to proceed, Pitney said.

Juneau is not connected to the road system and is accessible only by air or water. The project would provide access further north, but it would still require short ferry rides to connect travelers to Haines or Skagway.

The administration is allowing the Alaska Energy Authority, which has been pursuing the proposed Susitna dam, to continue to move the project through 2017, at which point it would be evaluated in the context of the state’s fiscal situation and other competing major capital projects.

Emily Ford, who is with the energy authority, said the goal is to preserve the investment that the state has already made, including finishing studies that are near completion and compiling collected data into reports.

More in News

Kenai City Manager Terry Eubank speaks during Kenai’s State of the City presentation at the Kenai Chamber of Commerce and Visitor Center in Kenai, Alaska, on Wednesday, April 2, 2025. (Jake Dye/Peninsula Clarion)
Services, projects spotlighted at Kenai’s State of the City

Mayor Brian Gabriel and City Manager Terry Eubank delivered the seventh annual address.

The Homer Public Library. File photo
In wake of executive order, peninsula libraries, museums brace for funding losses

Trump’s March 14 executive order may dismantle the Institute of Museum and Library Services “to the maximum extent consistent with applicable law.”

Cracks split the siding outside of Soldotna High School on Tuesday, Sept. 27, 2022 in Soldotna, Alaska. (Ashlyn O’Hara/Peninsula Clarion)
SoHi siding, Hope roof repair projects move forward

The Soldotna project has been reduced from its original scope.

Jacob Caldwell, chief executive officer of Kenai Aviation, stands at the Kenai Aviation desk at the Kenai Municipal Airport on Thursday, Sept. 13, 2022, in Kenai, Alaska. (Jake Dye/Peninsula Clarion)
Kenai Aviation selected to provide air service to Seward

Scheduled flights between Seward and Anchorage will begin May 1.

Monte Roberts, left, and Greg Brush, right, raise their hands during an emergency meeting of the Kenai River Special Management Area Advisory Board’s guide committee at the Kenai Peninsula Region Office of Alaska State Parks near Soldotna, Alaska, on Feb. 25, 2025. (Jake Dye/Peninsula Clarion)
KRSMA board pushes back on new guide stipulations, calls for public process

Stipulations 32 and 40 were included in an updated list emailed to Kenai River guides.

KPBSD Board of Education member Patti Truesdell speaks during a town hall meeting hosted by three Kenai Peninsula legislators in the Kenai Peninsula Borough Assembly Chambers in Soldotna, Alaska, on Saturday, March 29, 2025. (Jake Dye/Peninsula Clarion)
Education hot topic at local legislative town hall

More than 100 people attended a three-hour meeting where 46 spoke.

The Soldotna Field House is seen on a sunny Monday, March 31, 2025, in Soldotna, Alaska. (Jake Dye/Peninsula Clarion)
Field house work session set for April 9

A grand opening for the facility is slated for Aug. 16.

HEX President and CEO John Hendrix is photographed at Furie’s central processing facility in Nikiski, Alaska, on Wednesday, July 10, 2024. (Jake Dye/Peninsula Clarion)
Furie announces new lease to use Hilcorp rig, will drill this spring

A jack-up rig is a mobile platform that can be transported and deployed in different areas.

The ORPC proposed American Tidal Energy Project site is located at East Forland, Cook Inlet, just north of Nikiski, Alaska. Photo provided by ORPC
Marine energy developer pursues Cook Inlet tidal project

ORPC recently filed a draft pilot license application for a tidal energy project site near Nikiski.

Most Read