Voices of the Peninsula: Grant Lake hydro project needs better public input

  • By Hal Shepherd
  • Monday, November 10, 2014 4:06pm
  • Opinion

Homer Electric Association (HEA) staff and several hired consultants were in Moose Pass on Nov. 6 at a public meeting on environmental impact studies for the Grant Lake Hydro Electric Project. HEA went to great lengths to show that the Project will have virtually no impact on existing salmon habitat, and that once the facility goes on line, it will actually help fish. Indeed, the current version of the project, which no longer includes a dam, involves the use of outflow from Grant Lake that would be run through an underground tunnel to a penstock and power house located downstream on Grant Creek while storing peak flows from the creek to benefit habitat in tributaries.

Regardless of the win-win image of the Grant Lake Project HEA attempts to present, however, we may never know what sort of impacts it will have on water and salmon until it is too late because HEA has elected not to participate in the formal Integrated Licensing Process under Federal Energy Regulatory Act guidelines. While HEA consultants have discussed the studies with state and federal agencies through a series of meetings held in 2013 and 2014, this does not include the give-and-take between the licensee, the Federal Energy Regulatory Commission, other State, Federal and tribal government entities, conservation groups and other stakeholders of the formal process. Also, the ILP process requires the licensee to create a study plan that includes an intensive schedule of reports, meetings and multiple opportunities for stakeholder participation in the process (in the form of comments, challenges to the studies and appeals).

Indeed, the one and only chance for the public input on the Grant Lake studies, was a public meeting sponsored by HEA in Moose Pass near the Project location last week. Needless to say, HEA’s decision to ignore the formal study plan process did not go over well with most of the public participants at the meeting, in part because Moose Pass and Seward, which are outside of the HEA service area, will receive most of the potential environmental impacts and none of the energy benefits of the Project. Neither did it help that, regardless of the fact that if public comment is to be allowed at such events this is traditionally stated in the meeting notices, the Moose Pass participants were not informed that they could comment on the studies until after arriving at the meeting.

HEA attempts to downplay the almost non-existent public process related to the Grant Lake Project, by observing that the opportunity for the public input on the licensing decision starts in earnest with the draft licensing application which will be issued in early 2015. This conclusion, however, leaves out the fact that FERC, generally relies heavily on the results of the study plan when making licensing decisions. In this case, therefore, once FERC receives the study reports drafted, coordinated and controlled almost entirely by Project proponents, any licensing decision, along with the irreversible impacts on salmon and water would, likely, be a foregone conclusion.

More importantly, the proposed project is all that remains of what was once a proposal to build a network of multiple hydroelectric that would have industrialized the headwaters of the Kenai River watershed. This proposal was dropped only after a grass roots effort rose up in opposition to the hydropower network and its impacts to natural flows, the ecological and hydrological health of tributaries and cumulative impacts downstream. In the absence of public participation in the Grant Lake project, therefore, could the original project concept rear it’s ugly head once again?

Also, when HEA representatives are asked whether they plan to have a public meeting in Homer on the Project, the response is that they have been communicating to the public through meetings with the chamber of commerce, Rotary clubs and tables at public events. Could it be that HEA’s reluctance to obtain input on the project is because it has reserved the right to sell the energy to outside utilities and the project, ultimately may not even benefit HEA members?

Either way, needed are additional public meetings on the study plan so that the public can make an informed decision as to whether the project is appropriate and beneficial for the Kenai Watershed and HEA customers.

Hal Shepherd is director of the Center for Water Advocacy in Homer.

More in Opinion

Baisden family dog, Tug, is photographed in this undated photo. (Photo courtesy Rhonda Baisden)
Opinion: Ode to a good boy

The reality of saying goodbye hit us like a freight train

Alex Koplin. (courtesy photo)
Opinion: Why we’re not ranking Vance on the ballot

We will rank the other two candidates

Kenai Courthouse is photographed on Feb. 26, 2019, in Kenai, Alaska. (Clarion file)
Opinion: Seeking justice for our son

These state troopers need to be held accountable for their actions, and never let this happen again

Mark Sabbatini / Juneau Empire file photo
U.S. Sen. Lisa Murkowski talks to supporters during a campaign event at Louie’s Douglas Inn on Oct. 12, 2022.
Opinion: Murkowski must get off the ‘none of the above’ fence

She needs to follow Cheney’s lead and endorse Harris

This November 2022 file photos shows Alaska Division of Elections Director Gail Fenumiai explaining the ranked choice tabulation for the 2022 U.S. House race. Democratic incumbent Mary Peltola prevailed over Republican former Gov. Sarah Palin by a final tally of 54.9% to 45.1% after lower-finishing candidates Republican Nick Begich III amd Libertarian Chris Bye were eliminated during the first two rounds of instant choice runoffs. (Mark Sabbatini/Juneau Empire file)
Opinion: Ranked choice voting and open primaries diminish political party control. That’s great for Alaska.

The fact that both private political organizations are opposed to open primaries and RCV should be a red flag for us all

Voting booths are set up at the Soldotna Regional Sports Complex on Tuesday, Oct. 4, 2022, in Soldotna, Alaska. (Ashlyn O’Hara/Peninsula Clarion)
A few votes can make all the difference

Because we are expecting a low voter turnout, your vote carries more weight

Sen. Jesse Bjorkman, R-Nikiski, speaks during a debate with Rep. Ben Carpenter organized by the District 8 Alaska Republican Party at the Soldotna Regional Sports Complex in Soldotna, Alaska, on Monday, Aug. 12, 2024. (Jake Dye/Peninsula Clarion)
Opinion: Legislation encourages professional development for teachers

This bill provides incentives to teachers to seek the most rigorous and effective professional development they can.

Alex Koplin. Photo courtesy of Alex Koplin.
Point of View: The 2020 election was safe and secure

How can so many voters be so misinformed?

The Kenai Safeway is seen on Wednesday, July 20, 2022. (Camille Botello/Peninsula Clarion)
Opinion: AG’s silence on Kroger-Albertsons merger is failing Alaskans

We are concerned for all Alaskan consumers and for Alaska’s food security.

AKPIRG logo. Photo courtesy of AKPIRG
Opinion: With the right regulations, the SAVE Act can unlock energy prosperity in Alaska

Since 2010, only homeowners have been able to invest in and earn monthly bill savings from rooftop solar

The Safeway supermarket in Juneau, seen here Oct. 4, 2023, is among those in Alaska scheduled to be sold if its parent company, Albertsons Companies Inc., merges with Kroger Co., the parent company of Fred Meyer. (Mark Sabbatini / Juneau Empire file photo)
Opinion: Alaska’s attorney general flunks math test

One supermarket owner is less competitive than two, and more competition is good for shoppers

Jenny Carroll (Courtesy)
Opinion: Homer Harbor plays critical role in community, economy

This gateway to Cook Inlet fuels everything from recreation and food security to commercial enterprises