Schedule slipping on pre-FEED work

State officials say they are worried that the schedule for the big Alaska LNG Project could slip because of delays by North Slope producers in reaching key agreements.

However, the state itself is contributing to some of the delay, as well as part of the cost increase of the pre-front end engineering and design, or pre-FEED, sources familiar with the project say.

Gov. Bill Walker had hoped to have the agreements earlier this fall in time for legislative approval in a special session of the Legislature held in late October, but that did not happen.

The governor did present a proposal that the state buy out the interests of TransCanada Corp. in the project, which lawmakers approved.

Several big issues remain, however.

“We’re not making progress on the commercial agreements needed and this could be costly to the project timeline,” Alaska Natural Resources Deputy Commissioner Marty Rutherford said in a recent briefing to legislators.

The Alaska LNG Project involves an 800-mile, 42-inch pipeline from the North Slope to a large gas liquefaction plant in southern Alaska, along with a large gas treatment plant on the North Slope that would mainly remove carbon dioxide from the produced gas.

AGDC is the state corporation that represents Alaska’s 25 percent interest in Alaska LNG Project.

The project has been given federal approvals to export up to 20 million tons of LNG yearly. Construction costs are estimated between $45 billion and $65 billion.

Frequent changes in the state’s gas negotiating team by Walker have created uncertainty for the industry negotiating partners, the sources said, who asked not to be identified.

The governor has made three changes of his lead negotiator since earlier this year. Rutherford, at DNR, was the lead of the gas team until late spring, when Walker requested that Audie Setters, an experienced, retired Chevron LNG official, take over the role.

Setters had been working as a consultant for the state. He was replaced in the summer by Rigdon Boykin, a retired California attorney who now lives in South Carolina, and who had worked with the governor in prior years on the Alaska Gasline Port Authority, a group Walker headed.

Boykin was sent home to South Carolina by Walker the week of Nov. 9.

Boykin’s departure was not announced and no replacement was named but sources told the Journal that key decisions on the negotiations are now being made by three officials: Attorney General Craig Richards, Revenue Commissioner Randy Hoffbeck and Rutherford.

The schedule is slipping in other ways. It looks now that preliminary engineering now underway will not be complete until mid-2016, instead of late 2015 or early 2016 as was hoped earlier.

Part of that delay is due to Walker, too. Late in the summer the governor requested the Alaska LNG Project team to reevaluate the use of 48-inch diameter pipe rather than 42-inch pipe.

Industry partners had earlier concluded that 42-inch pipe was optimal for shipping the known gas reserves, and that the pipe could be manufactured by several suppliers including steel mills in North America.

Walker argued, however, that there will eventually be much more gas found on the North Slope and that building in extra capacity, with bigger pipe, will be more efficient in the long run than handling expansions by building more compressor stations.

Industry partners in Alaska LNG agreed, some reluctantly, to the reassessment of the bigger pipe, which is adding $30 million to the pre-FEED cost and delaying its results.

The analysis of 48-inch pipe against 42-inch pipe is to be finished by March with the final evaluation to be done by May, according to sources.

The decision on the pipe size must be made before the decision to move to front-end engineering and design, or FEED, which is currently estimated to cost the project partners a combined $2 billion, of which the state would be responsible for a quarter, equivalent to its ownership stake.

All that means the FEED decision could be delayed to late 2016, Rutherford told legislators in the briefing.

However, industry partners in the gas project may also wait to see the outcome of the November 2016 state general election. That’s when voters will decide whether to approve a necessary constitutional amendment to allow the state to enter long-term fiscal agreements with the producers for the gas project.

Dan Fauske, CEO of the Alaska Gasline Development Corp., or AGDC, told its board in a briefing Nov. 12 that while the hoped-for schedule is slipping it is still within an overall timeline laid out by the partners, which calls for beginning of FEED no later than July 2017.

This could still allow a final investment decision in 2019 and project completion in 2025, which is the current plan.

Rutherford said the most critical agreements the governor wants by early December are a gas balancing agreement among North Slope producers BP, ConocoPhillips and ExxonMobil, who are partners with the state in the project, and a separate agreement to cover contingencies over a partner withdrawing from the project, she said.

The partner withdrawal agreement has been requested by Walker, who is concerned that if a partner pulls out of the project it could stymie others in proceeding.

Rutherford said the governor is pushing the producers to have the gas balancing and withdrawal agreements by Dec. 4, the date on which the project members are to vote to approve the 2016 budgets for completing the preliminary engineering.

“Meeting this goal will be a significant challenge,” Rutherford said.

AGDC Operations Vice President Joe Dubler said the balancing agreement is proving to be complex because gas for the project will come from two North Slope fields, Prudhoe Bay and Point Thomson, and there are differing percentages of ownership by the producers.

“They’ll get there, but it is taking time,” Dubler said in the Nov. 12 briefing to AGDC’s board.

Agreements for withdrawn partners are normal in big projects but Walker wants an added provision that guarantees that the withdrawing party will commit gas to the project, meaning that it would agree to sell to a buyer.

That is proving to be very difficult in the negotiations because it essentially involves an agreement to sell gas to an unknown buyer for an unknown price.

One option is that the state itself could buy the gas now owned by a withdrawing partner, but that could entail huge financial risks for the state, advisors to the Legislature have warned lawmakers.

Dubler told AGDC’s board Nov. 12 that the partners are working hard on an agreement and hope to have it by the governor’s Dec. 4 deadline.

Fauske said the Alaska LNG Project partners could vote on the 2016 pre-FEED budget without the withdrawn parties and gas balancing agreements but that the governor prefers to have them done. The state itself will vote on the budget, as a partner.

Meanwhile, Rutherford said a hard deadline the project faces is June 24, 2016. That is the day a proposed constitutional amendment on fiscal terms must be sent to the Division of Elections to appear on the November general election ballot.

By that time the Legislature must also have ratified the agreement between the state and North Slope gas producers that will fix state tax and royalty terms for a period of years, presumably the length of long-term contracts to sell Alaska LNG.

To be legal, the fiscal agreement will require an amendment to the state constitution. The constitution currently forbids the Legislature approving a guarantee that state taxes won’t change.

North Slope gas producers say the fiscal term deal is a “must-have” because of Alaska’s past record of frequently changing state taxes on oil production.

However, fiscal terms deal is proving to be another big sticking point in current negotiations, the governor has said in recent briefings.

At least one Slope producer is pushing to have it cover taxes on crude oil as well as gas, Walker said. The state is pushing back on that.

Assuming the fiscal terms deal agreement is eventually concluded it will have to be ratified by the Legislature next spring, most likely in an April or May special session following the end of state lawmakers’ regular 2016 session.

A constitutional amendment requires a two-thirds vote of both the state House and Senate and that must be done by June 20.

“If we don’t meet that the entire project schedule begins to slip,” Rutherford said, because the next general election for ratification of the amendment is November 2018, which would effectively delay the project two years.

Tim Bradner can be reached at tim.bradner@alaskajournal.com.

More in News

Vice President Kelly Cooper speaks during a meeting of the Kenai Peninsula Borough Assembly in Soldotna, Alaska, on Tuesday, July 8, 2025. (Jake Dye/Peninsula Clarion)
Borough considers seasonal sales tax rate

Borough sales tax would be modified from a flat 3% to a seasonal model of 4% in summer months and 2% in winter months.

The Kasilof River is seen from the Kasilof River Recreation Area, July 30, 2019, in Kasilof, Alaska. (Photo by Erin Thompson/Peninsula Clarion)
King salmon fishing on Kasilof to close Thursday

If any king salmon is caught while fishing for other species, they may not be removed from the water and must be released immediately.

Un’a, a female sea otter pup who was admitted to the Alaska SeaLife Center in June 2025, plays with an enrichment toy at the center in Seward, Alaska. Photo courtesy of the Alaska SeaLife Center
SeaLife Center admits 2 seal pups, 1 orphaned otter

The three pups join the Alaska SeaLife Center’s ‘growing’ patient list.

James Wardlow demonstrates flilleting a salmon with an ulu during a smoked salmon demonstration, part of Fish Week 2023, on Wednesday, July 19, 2023, at the Kenai National Wildlife Refuge Visitor Center in Soldotna, Alaska. (Jake Dye/Peninsula Clarion)
Refuge to celebrate all things fish during weeklong event

Fish Week will take place July 16-19.

President Zen Kelly speaks during a meeting of the Kenai Peninsula Borough School District Board of Education in Soldotna, Alaska, on Monday, July 7, 2025. (Jake Dye/Peninsula Clarion)
School board finalizes budget with deep cuts to programming, classrooms

Multiple members of the board said they were frustrated by the state’s failure to fund education.

Former KPBSD Finance Director Liz Hayes speaks during a Kenai Peninsula Borough School District budget development meeting at Kenai Central High School in Kenai, Alaska, on Wednesday, Feb. 19, 2025. (Jake Dye/Peninsula Clarion)
School district finance department earns national awards

The two awards are based on comprehensive reviews of the district’s budget and financial reporting.

Children leap forward to grab candy during a Fourth of July parade on South Willow Street in Kenai, Alaska, on July 4, 2025. (Photo courtesy Sarah Every)
Celebrating the 4th in the streets

Kenai comes out for annual Independence Day parade.

Fire crews respond to the Bruce Fire, July 4, 2025, in Soldotna, Alaska. (Alaska Division of Forestry)
Firefighting crews respond to wildfire outside Soldotna

The 8-acre fire and two “spot fires” of less than one acre each are located near Mile 102 and 103 of the Sterling Highway.

Most Read