Photo by Dan Balmer/Peninsula Clarion An employee with Endries Company stands on a new culvert being installed beneath Beaver Loop Road Monday. The Kenai Watershed Forum is overseeing the project that will allow juvenile fish to migrate from Beaver Creek to the Kenai River. Groundwater has delayed the completion of the project for three more weeks but expected to be done the second week in July. A section of the road has been closed, cutting residents off from the Kenai Spur Highway intersection.

Photo by Dan Balmer/Peninsula Clarion An employee with Endries Company stands on a new culvert being installed beneath Beaver Loop Road Monday. The Kenai Watershed Forum is overseeing the project that will allow juvenile fish to migrate from Beaver Creek to the Kenai River. Groundwater has delayed the completion of the project for three more weeks but expected to be done the second week in July. A section of the road has been closed, cutting residents off from the Kenai Spur Highway intersection.

Beaver Loop Road culvert project delayed three weeks

  • By DAN BALMER
  • Monday, June 16, 2014 11:13pm
  • News

For the past three weeks, Kenai residents Andrew and Sara Smith have had to drive 30 miles out of their way every day to get to work in Soldotna.

Sara Smith, who works at Lucky Raven Tobacco on the Kenai Spur Highway, lives half a mile down Beaver Loop Road from the Spur Highway intersection. But a road closure to replace a culvert between her house and the intersection has forced her to drive to the other end of Beaver Loop Road to Bridge Access Road and through Kenai instead. To make matters more complicated, their mailbox is on the other side of the construction site.

“I haven’t checked my mail in a week because I don’t have the extra gas to go all the way around and back after work at midnight,” she said. “It has been nothing but a pain in the butt.”

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The road closure is for a Kenai Watershed Forum project to replace a culvert to improve fish passage for tributaries to the Kenai River beneath Beaver Loop Road. Robert Ruffner, executive director of the watershed forum, said the old culverts were structurally deficient and prevented juvenile fish from accessing habitat.

Residents of Beaver Loop Road that have been cut off from access to the Spur Highway will have to wait longer before the road opens. The project, which was originally expected to be completed June 11, has been delayed another three weeks, because of complications with high levels of groundwater, Ruffner said.

The contractor, Endries Company from Soldotna, requested an extension from the Department of Transportation, which will complete the road after the culvert and water and sewer lines under the road have been completed, Ruffner said.

“The project is a little behind schedule,” Ruffner said. “The contractor had some challenges with water and sewer mains that they were installing and the amount of groundwater. The recent rain hasn’t helped much either.”

Kenai City Manager Rick Koch said the city expects the road to be open in time for the personal-use dipnet fishery, which opens July 10.

Pete Endries, the general contractor, said it’s inconvenient but his crew is working diligently to finish the job. He said he didn’t like that the reader board on the Spur Highway said the road would be open June 11.

“I don’t like to a have a timeline set because people get upset when projects don’t get completed in time,” Endries said. “The groundwater and weather has made a mess of things and my guys are working hard to finish.”

On Monday a crew of six used heavy equipment and pumps to remove groundwater, while half of the new culvert was in place. Endries said his team was waiting on some heavy equipment to arrive, which slowed down their progress.

Elaina Sedivy, who lives next door to the Smiths, said the road closure has affected her, but the crew has done what they can for the locals. Sedivy said she works at Soldotna Kids Early Learning Center on the Spur Highway and has to open the daycare at 6 a.m. To save her commute time she parks on the other side of the construction and walks around the hole in the road.

Andrew Smith said the delay is frustrating. He only has one car and has had to take his wife to work before he goes to work. His babysitter lives in Sterling and has to drive the long way to get to their house.

Andrew Smith said he is concerned the project will not be completed in time for the start of dipnet season, which would greatly impact Beaver Loop Road residents who could only use Bridge Access Road.

“They need to get this road open,” he said. “Nobody will be able to get out. There are going to be a lot of accidents. It’s going to shut down this whole area.”

 

Reach Dan Balmer at daniel.balmer@peninsulaclarion.com.

Photo by Dan Balmer/Peninsula Clarion High levels of groundwater has delayed the culvert replacement project on Beaver Loop Road that has pushed the completion timeline back three weeks before the section of road can be reopened.

Photo by Dan Balmer/Peninsula Clarion High levels of groundwater has delayed the culvert replacement project on Beaver Loop Road that has pushed the completion timeline back three weeks before the section of road can be reopened.

More in News

Sterling Elementary School students collect trash from the banks of the Kenai River near Bing’s Landing in Sterling, Alaska, during the 10th Annual Kenai River Spring Cleanup on Wednesday, May 14, 2025. (Jake Dye/Peninsula Clarion)
Cleaning up the mess that’s left behind

Students from six local schools combed for litter during the 10th Annual Kenai River Spring Cleanup.

Kenai City Hall on Feb. 20, 2020, in Kenai, Alaska. (Photo by Victoria Petersen/Peninsula Clarion)
Kenai land sales proposal delayed amid council concerns

The ordinance would amend city code to add new language allowing officers and employees to participate in property sales.

Greg Springer delivers a presentation on sockeye fishing during A Day at the River at Centennial Park in Soldotna, Alaska, on Saturday, May 10, 2025. (Jake Dye/Peninsula Clarion)
Gearing up for summer fishing

Trout Unlimited and the Kenai Watershed Forum host “A Day at the River.”

Tyson Cox speaks during a meeting of the Kenai Peninsula Borough Assembly in Soldotna, Alaska, on Tuesday, May 6, 2025. (Jake Dye/Peninsula Clarion)
Borough awards Homer schools improvements contracts

Funding for improvements to the Homer High School entrance comes out of the 2022 bond package.

A young girl digs for razor clams at the Ninilchik Beach in Ninilchik, Alaska, on Saturday, July 1, 2023. (Jake Dye/Peninsula Clarion)
East Cook Inlet clamming to remain closed for 2025

The causes of these conditions remain unknown but likely include effects from habitat changes and predation, officials said.

Graduates process into the 55th Annual Kenai Peninsula College Commencement Ceremony, held at Kenai Central High School in Kenai, Alaska, on Thursday, May 8, 2025. (Jake Dye/Peninsula Clarion)
‘The kinds of leaders Alaska and the world needs’

KPC graduates congratulated as they head into the next chapter of their lives.

Homer Electric Association General Manager Brad Janorschke speaks at the utility’s annual meeting of the members at Kenai Central High School in Kenai, Alaska, on Thursday, May 1, 2025. (Jake Dye/Peninsula Clarion)
HEA manager talks natural gas, hazard trees, rates at annual meeting

Natural gas remains the “backbone” of the utility’s energy production.

Most Read