Photo by Dan Balmer/Peninsula Clarion An employee with Endries Company stands on a new culvert being installed beneath Beaver Loop Road Monday. The Kenai Watershed Forum is overseeing the project that will allow juvenile fish to migrate from Beaver Creek to the Kenai River. Groundwater has delayed the completion of the project for three more weeks but expected to be done the second week in July. A section of the road has been closed, cutting residents off from the Kenai Spur Highway intersection.

Photo by Dan Balmer/Peninsula Clarion An employee with Endries Company stands on a new culvert being installed beneath Beaver Loop Road Monday. The Kenai Watershed Forum is overseeing the project that will allow juvenile fish to migrate from Beaver Creek to the Kenai River. Groundwater has delayed the completion of the project for three more weeks but expected to be done the second week in July. A section of the road has been closed, cutting residents off from the Kenai Spur Highway intersection.

Beaver Loop Road culvert project delayed three weeks

  • By DAN BALMER
  • Monday, June 16, 2014 11:13pm
  • News

For the past three weeks, Kenai residents Andrew and Sara Smith have had to drive 30 miles out of their way every day to get to work in Soldotna.

Sara Smith, who works at Lucky Raven Tobacco on the Kenai Spur Highway, lives half a mile down Beaver Loop Road from the Spur Highway intersection. But a road closure to replace a culvert between her house and the intersection has forced her to drive to the other end of Beaver Loop Road to Bridge Access Road and through Kenai instead. To make matters more complicated, their mailbox is on the other side of the construction site.

“I haven’t checked my mail in a week because I don’t have the extra gas to go all the way around and back after work at midnight,” she said. “It has been nothing but a pain in the butt.”

The road closure is for a Kenai Watershed Forum project to replace a culvert to improve fish passage for tributaries to the Kenai River beneath Beaver Loop Road. Robert Ruffner, executive director of the watershed forum, said the old culverts were structurally deficient and prevented juvenile fish from accessing habitat.

Residents of Beaver Loop Road that have been cut off from access to the Spur Highway will have to wait longer before the road opens. The project, which was originally expected to be completed June 11, has been delayed another three weeks, because of complications with high levels of groundwater, Ruffner said.

The contractor, Endries Company from Soldotna, requested an extension from the Department of Transportation, which will complete the road after the culvert and water and sewer lines under the road have been completed, Ruffner said.

“The project is a little behind schedule,” Ruffner said. “The contractor had some challenges with water and sewer mains that they were installing and the amount of groundwater. The recent rain hasn’t helped much either.”

Kenai City Manager Rick Koch said the city expects the road to be open in time for the personal-use dipnet fishery, which opens July 10.

Pete Endries, the general contractor, said it’s inconvenient but his crew is working diligently to finish the job. He said he didn’t like that the reader board on the Spur Highway said the road would be open June 11.

“I don’t like to a have a timeline set because people get upset when projects don’t get completed in time,” Endries said. “The groundwater and weather has made a mess of things and my guys are working hard to finish.”

On Monday a crew of six used heavy equipment and pumps to remove groundwater, while half of the new culvert was in place. Endries said his team was waiting on some heavy equipment to arrive, which slowed down their progress.

Elaina Sedivy, who lives next door to the Smiths, said the road closure has affected her, but the crew has done what they can for the locals. Sedivy said she works at Soldotna Kids Early Learning Center on the Spur Highway and has to open the daycare at 6 a.m. To save her commute time she parks on the other side of the construction and walks around the hole in the road.

Andrew Smith said the delay is frustrating. He only has one car and has had to take his wife to work before he goes to work. His babysitter lives in Sterling and has to drive the long way to get to their house.

Andrew Smith said he is concerned the project will not be completed in time for the start of dipnet season, which would greatly impact Beaver Loop Road residents who could only use Bridge Access Road.

“They need to get this road open,” he said. “Nobody will be able to get out. There are going to be a lot of accidents. It’s going to shut down this whole area.”

 

Reach Dan Balmer at daniel.balmer@peninsulaclarion.com.

Photo by Dan Balmer/Peninsula Clarion High levels of groundwater has delayed the culvert replacement project on Beaver Loop Road that has pushed the completion timeline back three weeks before the section of road can be reopened.

Photo by Dan Balmer/Peninsula Clarion High levels of groundwater has delayed the culvert replacement project on Beaver Loop Road that has pushed the completion timeline back three weeks before the section of road can be reopened.

More in News

tease
House District 6 race gets 3rd candidate

Alana Greear filed a letter of intent to run on April 5

Kenai City Hall is seen on Feb. 20, 2020, in Kenai, Alaska. (Photo by Victoria Petersen/Peninsula Clarion)
Kenai water treatment plant project moves forward

The city will contract with Anchorage-based HDL Engineering Consultants for design and engineering of a new water treatment plant pumphouse

Students of Soldotna High School stage a walkout in protest of the veto of Senate Bill 140 in front of their school in Soldotna, Alaska, on Wednesday, April 17, 2024. (Jake Dye/Peninsula Clarion)
SoHi students walk out for school funding

The protest was in response to the veto of an education bill that would have increased school funding

The Kenai Courthouse as seen on Monday, July 3, 2023, in Kenai, Alaska. (Ashlyn O’Hara/Peninsula Clarion)
Clam Gulch resident convicted of 60 counts for sexual abuse of a minor

The conviction came at the end of a three-week trial at the Kenai Courthouse

The Kenai Peninsula Borough Assembly meets in Seward, Alaska, on Tuesday, April 16, 2024. (screenshot)
Borough awards contract for replacement of Seward High School track

The project is part of a bond package that funds major deferred maintenance projects at 10 borough schools

Kenai Peninsula Education Association President LaDawn Druce, left, and committee Chair Jason Tauriainen, right, participate in the first meeting of the Kenai Peninsula Borough School District’s Four Day School Week Ad Hoc Committee on Wednesday, Jan. 10, 2024, in Soldotna, Alaska. (Ashlyn O’Hara/Peninsula Clarion)
4-day school week committee talks purpose of potential change, possible calendar

The change could help curb costs on things like substitutes, according to district estimates

A studded tire is attached to a very cool car in the parking lot of the Peninsula Clarion in Kenai, Alaska, on Monday, April 15, 2024. (Jake Dye/Peninsula Clarion)
Studded tire removal deadline extended

A 15-day extension was issued via emergency order for communities above the 60 degrees latitude line

A sign for Peninsula Community Health Services stands outside their facility in Soldotna, Alaska, on Monday, April 15, 2024. (Jake Dye/Peninsula Clarion)
PCHS to pursue Nikiski expansion, moves to meet other community needs

PCHS is a private, nonprofit organization that provides access to health care to anyone in the community

Jordan Chilson votes in favor of an ordinance he sponsored seeking equitable access to baby changing tables during a meeting of the Soldotna City Council in Soldotna, Alaska, on Wednesday, April 10, 2024. (Jake Dye/Peninsula Clarion)
Soldotna OKs ordinance seeking to increase access to baby changing tables

The ordinance requires all newly constructed or renovated city-owned and operated facilities to include changing tables installed in both men’s and women’s restrooms

Most Read