AGDC releases plan for gas pipeline off-takes

  • By Tim Bradner
  • Sunday, June 21, 2015 10:47pm
  • News

The state-owned Alaska Gasline Development Corp. has developed preliminary designs for “offtake” facilities that would allow communities to take natural gas from a large-diameter gas pipeline, if one were built.

The designs were presented to AGDC’s board of directors at its June 11 meeting.

Under legislation allowing the state to participate in the large Alaska LNG Project, the state has the responsibility to designate up to five gas “offtake” points for communities along the pipeline route, and to assist in developing facilities including lateral pipelines, such as one planned to be built to Fairbanks from the route of the large gas pipeline.

So far, offtakes have been designated at points near Fairbanks, a “North Cook Inlet” location (presumably in the Matanuska-Susitna Borough) and a “South Cook Inlet” point, near Nikiski on the Kenai Peninsula.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Nikiski is also the location of a planned large gas liquefaction plant for the project, which would produce LNG for export markets.

The facilities to extract gas, condition it and transport the gas to communities and condition the gas for home heating or local power generation are not the responsibility of the Alaska LNG Project.

AGDC, the state corporation, has been given that responsibility. Preliminary plans for offtake facilities presented to the corporation’s board June 11 include four possible designs. One is a “macro” off-take facility that could handle 80 million cubic feet to 330 million cubic feet per day, and that could cost $37.6 million. A second is a “mini” offtake unit that would handle 20 million cubic feet to 75 million cubic feet per day, and that could cost $28 million.

A third is a “micro” offtake facility that would handle 400,000 cubic feet to 2 million cubic feet per day, with an estimated cost of $14.8 million. The fourth is a “nano” unit that would handle 40,000 cubic feet to 250,000 cubic feet per day, and that would cost $13.8 million.

Meanwhile, AGDC has also taken a first cut at what the possible in-state demand for gas might be from the North Slope. This is important for the Alaska LNP Project planners to know because they must be able to assure that supplies will be available for LNG export customers.

Forecasting this is complicated, however, because it must be assumed that Cook Inlet will continue to produce gas for in-state use.

AGDC’s board was told June 11 that the possible in-state demand for North Slope gas might be about 70 billion cubic feet of gas yearly in 2030, five years after the project is to start up, and increasing to about 100 billion cubic feet of gas per year by 2040.

The assumption included in the forecast is that Cook Inlet production will decline from its current rate of about 100 billion cubic feet of gas per year to about 44 billion cubic feet of gas per year by 2030 and 25 billion cubic feet of gas per year by 2040, therefore increasing the demand for North Slope gas.

This is a “base case” that assumes no large new Cook Inlet discoveries and only one major new industrial customer, the Donlin Gold project. There is also a high demand case, however, that includes possible new mines being developed.

In another development, the state gas corporation has officially put Gov. Bill Walker’s plan for an expanded state-led gas pipeline on the shelf.

“We’ll be holding this in abeyance,” said board chairman John Burns at the meeting.

Walker had asked the corporation to pursue engineering studies to expand a smaller gas pipeline plan but the Legislature, in a budget move, took $157 million from AGDC’s budget that would have been used for the work and re-appropriated it to support schools.

Staff to the gas corporation had meanwhile prepared estimates for the upsizing engineering costs for the board but did not formally present them given the Legislature’s action.

Also, an engineering and design consortium AGDC had hoped to use for the redesign for a scaled-up project, which was under contract for design and engineering for the gas treatment plant for the smaller pipeline, has now been demobilized, the board was told.

Remobilizing the team would add to costs of the engineering.

For several years AGDC has been working on a plan for a smaller 500 million-cubic feet per day pipeline from the North Slope that would serve as a backup to get gas to Alaska communities in case the large Alaska LNG Project is not built.

The engineering and design work on that project, known as the Alaska Stand-Alone Pipeline, or ASAP, is now complete and a supplemental environmental impact statement required because of design changes is due to be complete in 2016. The project is essentially ready to go if it needed.

Walker had wanted to increase the scope of ASAP, however, so that it could carry gas volumes similar to those in the larger industry-led project. That unleashed a barrage of criticism, however, from legislators and others that the governor wanted a state-led pipeline in competition with the industry project.

Despite that furor, the work on the smaller state pipeline has yielded positive benefits for the larger gas project, in which the state is a 25 percent partner.

The routes of both pipeline are now aligned to follow the same rights-of-way, which means that the Alaska LNG Project can benefit from environmental and technical work done by AGDC for its smaller pipeline.

“This is a huge benefit for Alaska LNG,” said Dave Cruz, an Alaska contractor and board member of AGDC who chairs the board’s technical review committee.

“There has been good science and good data that has been generated, and Alaska LNG has accepted it.”

The Legislature had earlier appropriated $305 million for ASAP to do engineering and permitting sufficient to get the smaller project to a construction decision. About $118 million of that has been spent to date, leaving $187 million. That is now reduced by $157 million due to the Legislature’s re-appropriation this spring, however.

Meanwhile, $48 million authorized earlier this year for AGDC’s remaining work on ASAP, of which $28 million has been spent to date, is on projects that also benefit the larger pipeline. On work that benefits both projects, Alaska LNG Project pays 80 percent, the AGDC board was told.

The state corporation is also undertaking geotechnical work this summer on behalf of the industry-led project, taking advantage of special, streamlined permit authority on state lands given the gas corporation by the Legislature.

On work like this that is solely on behalf of Alaska LNG, the consortium reimburses AGDC for 100 percent of its costs, although the state might pay part of that if it involves work at the LNG plant, in which the state is a full 25 percent partner. The state is in a partnership with TransCanada Corp. on the pipeline and North Slope gas conditioning plant.

Tim Bradner can be reached at tim.bradner@alaskajournal.com.

More in News

Member Tom Tougas, far right, speaks during a meeting of the Kenai Peninsula Borough Tourism Industry Working Group in Soldotna, Alaska, on Wednesday, Dec. 18, 2024. (Jake Dye/Peninsula Clarion)
Tourism working group rejects bed tax, recommends seasonal sales tax adjustment

The document includes a section that says the borough could alternatively leave its tax structure exactly as it is.

The rescued sea otter pup looks at the camera in this undated picture, provided by the Alaska SeaLife Center. (Kaiti Grant/Alaska SeaLife Center)
Stranded otter pup rescued from Homer beach

She is estimated to be around 2 months old and was found alone by concerned beach walkers.

Kenai Peninsula College Director Cheryl Siemers speaks to graduates during the 55th commencement ceremony at Kachemak Bay Campus on Wednesday, May 7, 2025, in Homer, Alaska. (Delcenia Cosman/Homer News)
Kenai Peninsula College leadership sees temporary transitions

KPC Director Cheryl Siemers is serving as interim UAA chancellor, while former KBC director Reid Brewer fills in her role.

Ash-Lee Waddell (center) of Homer is one of six recipients of the 2025 First Lady’s Volunteer Award at the Governor’s Residence in Juneau, Alaska, on May 13, 2025. Photo courtesy of the Office of the Governor
First lady honors Alaska volunteers

Volunteers from Homer and Nikiski were recognized.

The front of the Kenai Police Department as seen on Dec. 10, 2019. (Photo by Brian Mazurek/Peninsula Clarion)
Update: Middle schooler reported missing found after 24-hour search

The student was seen leaving Kenai Middle School at around 10:30 a.m. Wednesday.

The Oceania Riviera stands out against a bluebird sky at the Homer Harbor on Wednesday, May 7, 2025. Over 1200 passengers from aboard the boat explored Homer throughout the beautiful day. (Chloe Pleznac/Homer News)
Homer tourism season kicks off with arrival of cruise ships

The first cruise ship of the season arrived April 28 with 930 passengers.

tease
‘Tomorrow — remember you are still a learner’

Kachemak Bay Campus graduated 49 students during its 55th annual commencement hosted on May 7.

Mt. Redoubt rises above Cook Inlet and the Anchor River drainage as fireweed is in bloom, as seen from Diamond Ridge Road on Friday, July 22, 2022, near Homer, Alaska. (Photo by Michael Armstrong/Homer News)
Native plants provide lifeline for local songbirds

Shorebird Festival talk highlights importance of native plants.

Sterling Elementary School students collect trash from the banks of the Kenai River near Bing’s Landing in Sterling, Alaska, during the 10th Annual Kenai River Spring Cleanup on Wednesday, May 14, 2025. (Jake Dye/Peninsula Clarion)
Cleaning up the mess that’s left behind

Students from six local schools combed for litter during the 10th Annual Kenai River Spring Cleanup.

Most Read