Cars can be seen lined up on the Sterling Highway, Alaska, on Saturday, Sept. 7, 2019. (Photo by Brian Mazurek/Peninsula Clarion)

Cars can be seen lined up on the Sterling Highway, Alaska, on Saturday, Sept. 7, 2019. (Photo by Brian Mazurek/Peninsula Clarion)

Construction crews on Sterling Highway making up for lost time

Closures caused by the Swan Lake Fire hindered progress for about two weeks

Recent closures on the Sterling Highway due to fire activity have left road crews scrambling to finish a major construction project before winter.

This summer, the Alaska Department of Transportation and Granite Construction have been working to improve road conditions on the Sterling Highway from Mile 58 to Mile 79, between Sterling and Cooper Landing.

The Swan Lake Fire — which has been burning in the Kenai National Wildlife Refuge between Sterling and Cooper Landing since June 5 — crossed the highway on Aug. 18 and prompted public safety officials to halt construction and close the road to traffic. Throughout the week of Aug. 18, the road was closed intermittently as fire crews worked to mitigate fire danger and heavy smoke conditions severely limited visibility at times.

Eventually, traffic resumed on the highway with pilot cars guiding motorists, and by the morning of Sept. 3 construction crews were back to work.

DOT Project Engineer Shaun Combs said on Thursday that fire activity did delay progress on the project, but the estimated completion date — June 15 of next year — remains the same. The work wasn’t completely halted, and crews were able to make some progress on installing new signage and wildlife fencing from Mile 72 to Mile 79 when fire activity permitted.

Now that construction crews are back on the road, Combs said the main goal is to finish paving the top and bottom layers of asphalt before winter. Progress will be entirely dependent on weather conditions for the month of September, and Combs said that the current drought conditions could give crews the extra few weeks needed to make up for lost time.

“We essentially lost two weeks of prime paving weather,” Combs said. “So now we’re focused on putting the final icing on the cake, with the goal of having the traveling public on that top asphalt surface by winter.”

After the fire moved through the area, trees along the roadway had their root systems burnt out and were left susceptible to falling over in windy conditions. Combs said that crews are aware of the dangers of falling trees and are equipped with chain saws to mitigate any dangers in the area. Protective rollover bars are installed on all the vehicles and heavy machinery to further ensure the crew members’ safety.

Combs expects paving crews to begin work at Mile 58 on Tuesday, barring any significant rain.

Motorists should be aware of crews and firefighters working day and night, and pilot cars will be in use during paving operations.

Further down the Sterling Highway, DOT crews are finishing up work between Mile 97 and Mile 118 between Soldotna and Clam Gulch. Installation of four large-diameter culverts at Slikok Tributary, Crooked Creek, Clam Gulch and Coal Creek has been completed. The Sterling Highway is open to all traffic at the Crooked Creek detour.

Motorists should be aware of possible delays when seeding trucks are on the roadway, and a high number of moose have been sighted along the project corridor.

Crews are working day and night on this project, which is scheduled to be completed in October of this year.

Beaver Loop Road will be closed from Bridge Access Road to Barbara Drive starting Monday, Sept. 16 and ending Sunday, Sept. 29. Local access will be maintained in the area, but no through traffic will be allowed.

DOT is working with QAP to resurface the entirety of Beaver Loop Road and construct additional turn lanes, as well as a pedestrian pathway.

Through late September, crews will be building the pedestrian path, replacing pipes and rebuilding the section of Beaver Loop Road between Bridge Access Road and Barbara Drive. Construction on this project is expected to last through the end of the season.

On the Kenai Spur Highway, DOT is working with Wolverine Construction to expand the highway to five lanes from Mile 5 to Mile 8 between Sports Lake Road and Swire Road.

Crews are working on and off the roadway in this area from 7 a.m. to 7 p.m. An alternate traffic pattern is in place and drivers should use caution and reduce speed when traveling through the area. Drivers should also be aware of potential pilot car operations and follow posted detours for side road closures.

The Kenai Spur Highway construction is expected to last through the season.

Visit 511.alaska.gov for the latest traffic information and visit alaskanavigator.org for the latest construction updates.

More in News

A studded tire is attached to a very cool car in the parking lot of the Peninsula Clarion in Kenai, Alaska, on Monday, April 15, 2024. (Jake Dye/Peninsula Clarion)
Studded tire removal deadline extended

A 15-day extension was issued via emergency order for communities above the 60 degrees latitude line

A sign for Peninsula Community Health Services stands outside their facility in Soldotna, Alaska, on Monday, April 15, 2024. (Jake Dye/Peninsula Clarion)
PCHS to pursue Nikiski expansion, moves to meet other community needs

PCHS is a private, nonprofit organization that provides access to health care to anyone in the community

Jordan Chilson votes in favor of an ordinance he sponsored seeking equitable access to baby changing tables during a meeting of the Soldotna City Council in Soldotna, Alaska, on Wednesday, April 10, 2024. (Jake Dye/Peninsula Clarion)
Soldotna OKs ordinance seeking to increase access to baby changing tables

The ordinance requires all newly constructed or renovated city-owned and operated facilities to include changing tables installed in both men’s and women’s restrooms

Joel Caldwell shows off the new Tecnam Traveller on Thursday, Sept. 15, 2022, in Kenai, Alaska. Kenai Aviation has since added two more Tecnam Travellers to its fleet. (Jake Dye/Peninsula Clarion)
Kenai Aviation adds 3rd plane to commuter service, readies for busy summer schedule

Kenai Aviation plans to increase its schedule to include 18 flights a day running seven days a week

Jake Dye/Peninsula Clarion
Kelley Cizek, right, speaks as Jason Tauriainen, Patti Truesdell and Penny Vadla listen during a special meeting of the Kenai Peninsula Borough School District’s school board in Soldotna on Monday.
‘They deserve better than this’

School board passes budget with broad swath of cuts, including pools, theaters and some support staff

The Alaska State Capitol on Friday, March 1, 2024, in Juneau, Alaska. (Ashlyn O’Hara/Peninsula Clarion)
Alaska House passes budget with roughly $2,275 payments to residents, bill goes to Senate

The bill also includes a roughly $175 million, one-time increase in aid to school districts that would be paid according to a funding formula

The Kenai River flows near Soldotna Creek Park in Soldotna, Alaska, on Wednesday, April 10, 2024. The Riverfront Redevelopment project will impact much of Soldotna’s riverside areas downstream to the bridge. (Jake Dye/Peninsula Clarion)
Soldotna riverfront redevelopment planning moves forward

Soldotna City Council on Monday unanimously approved the creation of a project manager to shepherd the Riverfront Redevelopment Project

Jake Dye/Peninsula Clarion
Corey Cannon, who plays baseball as part of Soldotna Little League, speaks to the Soldotna City Council during their meeting in Soldotna on Wednesday.
Soldotna Little League receives donation for facility repairs

The city owns the fields, but the Little League leases the land and is responsible for the maintenance of the facilities

Aleutian Airways logo. Photo courtesy of Aleutian Airways
Aleutian airways to halt Homer service during runway project

Service will be suspended beginning April 15

Most Read